How Can We Help?
Original Credit/Original CV
The rate is calculated by taking estimate insurance calc value divided by the self-performed original CV (as long as this is not the GC, this is the contract value entered at the contract level minus the sum of the contract values directly beneath the contract) times the change order value listed higher on the page.
Original Credit/Original Payroll
The rate is calculated by taking the estimated insurance calculation value divided by the estimate payroll (from the est insurance calc) times the change order value listed higher on the page.